Bond Claims in Ontario Construction Disputes

Crane over unfinished building

The company that owes you money for your construction work has gone quiet, or gone under, and your lien has expired or was never worth much. A construction bond claim is the route that depends on neither. It runs against a surety’s own promise, on its own timetable, and it reaches money a lien cannot. This guide covers the three bonds you may be looking at, the deadlines that decide these claims, and what the surety will say back.

Three Bonds, and Only One Supports a Construction Bond Claim

Name the instrument correctly first, because the three in common use answer to different people.

A labour and material payment bond pays trades and suppliers, so this is what people in the construction business want as protection against unpaid invoices. A public owner holds it on a public contract and the general contractor often holds it on private work, yet either way it protects the unpaid claimants further down the chain.

A performance bond answers to the obligee (the project owner or entity requiring the bond). If the contractor defaults, the surety (typically an insurance company) may remedy the default, complete the contract, obtain completion bids or simply pay. A subcontractor gets nothing from it, however badly the project was managed.

A bond posted under section 44 of the Construction Act is different again. It is substituted security: once the registration is vacated the lien stops attaching to the premises and to the holdbacks, and charges the posted security instead. It is not a payment remedy, and treating it as one is the commonest mix-up here.

What a Construction Bond Claim Actually Runs Against

The bond is a contract, so its own wording decides almost everything.

On a public project the regulations prescribe that wording. Form 31 reaches anyone with a direct contract with the contractor, and also parties who contracted with a subcontractor, which covers a tier that private forms often leave out.

That distinction decides whether you have a construction bond claim at all. A standard industry form frequently defines a claimant as someone holding a direct contract with the principal, so a supplier to a subcontractor falls outside it before anyone looks at the merits.

Two clocks, triggered by different events

Form 31 makes notice a condition precedent. Ordinary amounts need notice within 120 calendar days after the claimant last performed labour or provided materials, and holdback within 120 calendar days after the claimant should have been paid in full.

The second clock belongs to somebody else. Any suit against the surety must start within one year of the date on which the contractor last performed work on the contract, and warranty work counts.

That mismatch cuts both ways in a construction bond claim. Your notice deadline runs from your own last day, so it can expire while the contractor is still on site and the project still looks healthy. Conversely, where the contractor demobilizes or collapses early, the one-year suit period may already be running before you have even quantified the claim.

Neither clock has anything to do with lien deadlines, which run on their own triggers. Preserving a lien therefore protects nothing under the bond.

Public Projects: the Bond Is Mandatory

Section 85.1 of the Act requires bonding on a public contract, meaning a contract between a contractor and an owner that is the Crown, a municipality or a broader public sector organization. It does not apply where the contractor is an architect or engineer.

Section 12 of O. Reg. 304/18 sets the threshold at a contract price of $500,000 or more, and section 85.1 requires each bond to cover at least 50 per cent of that price unless the regulations prescribe another percentage.

A lien behaves differently on some of that land. Under section 16 a lien never attaches to the Crown’s interest, and on Crown premises or a public street or highway owned by a municipality it charges the holdback and other amounts owing instead of title. Other municipal land, and land held by broader public sector organizations, stays lienable in the ordinary way, so a construction bond claim is an additional remedy there and frequently the more valuable one.

One recent change matters to a construction bond claim. A revised Form 31 took effect on January 1, 2026 and confirms that a sub-subcontractor need not preserve or perfect a lien, although its recovery stays capped at what the contractor would owe under the Act.

What the Surety Will Say Back

Sureties defend a construction bond claim properly, and three answers do most of the work.

Late or inaccurate notice. In Wessuc Inc. v. Todd Brothers Contracting Ltd., 2024 ONSC 4368, a subcontractor on a municipal sewage lagoon project lost a $1.7 million claim and had to pay $53,000 on the contractor’s counterclaim. The court went on to say that notice outside the 120 days, substantially inaccurate when it came, would have sunk the construction bond claim anyway, and that it would have refused relief from forfeiture given the claimant’s own unreasonable conduct, despite the surety suffering no prejudice.

No underlying debt. That case turned on a simpler point first. A surety promises to answer for the principal’s obligation, so where the claim against the contractor failed, the construction bond claim failed with it.

Attacks on the bond itself. In Urban Mechanical Contracting Ltd. v. Zurich Insurance Company Ltd., 2022 ONCA 589, a surety sought rescission of bonds it said fraud had procured. Subcontractors and the project’s lenders, who had relied on the bonds, applied to stop that as innocent third parties, and the Court of Appeal dismissed their appeals, holding their interests are not an absolute bar to rescission. It did not decide that the bonds fell and left that question for the action itself.

Finally, remember the ceiling on any construction bond claim. The surety never owes more than the bond amount, and every payment reduces what remains for everyone behind you.

What to Do Next: When to Call a Lawyer

Find out whether a bond exists before anything else, because nobody volunteers one and the documents you hold will not mention it.

Section 39 of the Act is how you ask. A person who holds a lien, is a beneficiary of a trust under Part II or a mortgagee may demand a copy in writing, and most unpaid trades and suppliers qualify as trust beneficiaries. The recipient must answer within a reasonable time not exceeding twenty-one days and is liable in damages for a failure or a misstatement.

That step is not housekeeping. In Valard Construction Ltd. v. Bird Construction Co., 2018 SCC 8, a sub-subcontractor learned of a payment bond only after the notice period had expired, and the surety denied the claim. The Supreme Court allowed the appeal and held that the general contractor, as obligee, held the bond in trust and on those facts had to take reasonable steps to tell beneficiaries it existed. That case arose on an Alberta project, and the claim that reached the Court was against the contractor rather than the surety.

So diarise both bond dates separately from your lien dates, and ask the contractor in writing when it expects to finish, since its last day of work, warranty work included, governs your limitation period.

Then give notice early and get it right. A construction bond claim turns on a document that costs nothing to send and that nobody can repair afterwards.

Bonds are the quiet part of Ontario construction law, and a construction bond claim is frequently the only money left when a payer collapses. If a bonded project owes you, contact Cowan before either clock runs out.