The Doctrine of Frustration in Commercial Contracts

Empty Retail Store

A pandemic lockdown closes your store, a new law blocks the deal, or a regulator changes the rules halfway through. Business owners in that position often reach for the doctrine of frustration, which would enable them to get out of the contract without paying, but Ontario courts usually say no. The doctrine is real, but it is deliberately narrow. This guide covers what it requires, why most frustration arguments fail, and what happens to the money when one succeeds.

What the Doctrine of Frustration in Ontario Requires

The doctrine of frustration in Ontario is not a remedy for a bad bargain. It ends a contract only where something happens after signing that neither side caused, that the contract does not deal with, and that makes performance fundamentally different from what the parties promised.

Ontario courts take the test from the Supreme Court of Canada. In Naylor Group Inc. v. Ellis-Don Construction Ltd., 2001 SCC 58, the Court put it this way at paragraph 53:

Frustration occurs when a situation has arisen for which the parties made no provision in the contract and performance of the contract becomes “a thing radically different from that which was undertaken by the contract” …

Naylor, an Ontario case, also shows how hard the doctrine of frustration is to satisfy. Ellis-Don, a general contractor, carried Naylor’s electrical bid in its winning tender for a hospital project. The Ontario Labour Relations Board then upheld a union grievance and confirmed that Ellis-Don could use only electrical subcontractors whose workers belonged to that union, and Ellis-Don gave the work to someone else.

Ellis-Don argued that the ruling frustrated its bargain with Naylor. The Supreme Court disagreed, because the ruling was foreseeable and merely confirmed an obligation Ellis-Don already had. Naylor recovered damages instead.

What Does Not Frustrate a Contract

Most frustration arguments fail for one of four reasons.

It just got more expensive. In Perkins v. Sheikhtavi, 2019 ONCA 925, a buyer made an unconditional $1,871,000 offer on a house in 2017. Ontario then announced its non-resident speculation tax, local prices fell, and she could neither sell her own home nor finance the purchase.

The Court of Appeal accepted that the announcement was a supervening event. However, it did not make performance radically different, and the buyer had chosen to go firm, so the risk was hers. The sellers kept their judgment for the shortfall on resale, plus carrying costs.

The contract already dealt with it. Where the parties saw a risk and provided for it, the doctrine has nothing to fill, because the clause governs instead. That was another reason Ellis-Don lost: the bid terms already let it reasonably object to a subcontractor, so the parties had built their own exit for changed circumstances.

It was foreseeable. Under the doctrine of frustration, Ontario courts weigh foreseeability heavily. A risk the parties could see coming and chose not to address rarely frustrates anything, as the Court of Appeal confirmed in Perkins. The Supreme Court also relied on the foreseeability of the ruling in Naylor.

One side caused it. The event must happen without the fault of either party. A business cannot use the doctrine of frustration in Ontario to escape a problem of its own making.

The pandemic test case

The pandemic produced a wave of arguments under the doctrine of frustration, and in commercial disputes Ontario courts have generally rejected them. In Braebury Development Corp. v. Gap (Canada) Inc., 2021 ONSC 6210, a landlord sued Gap for more than $200,000 in rent arrears on a Kingston store, and Gap argued that the lockdowns frustrated the lease.

The court disagreed. The forced closure was temporary, the lease allowed any retail use, and its force majeure clause showed the parties had contemplated disruption while expressly preserving the obligation to pay rent. The landlord obtained summary judgment.

That last point deserves attention. Read the force majeure clause before arguing frustration, because a clause that covers the event will usually decide the dispute on its own terms.

When the Doctrine of Frustration Succeeds in Ontario

It does happen. Capital Quality Homes Ltd. v. Colwyn Construction Ltd. (1975), 9 O.R. (2d) 617 (C.A.), remains the classic Ontario example of the doctrine of frustration at work.

A buyer agreed to purchase 26 building lots, each with its own deed so that the buyer could build and sell a home on each one. Before closing, new planning legislation barred conveying the lots separately without planning consent. Because separate conveyances were the shared purpose of the deal, the Court of Appeal held the contract frustrated.

Notice the pattern. A change in the law destroyed the purpose of the transaction rather than simply making it less profitable, and neither party had provided for it.

What Happens to the Contract and the Money

The doctrine of frustration in Ontario ends a contract differently from a breach. When one side repudiates, the other chooses whether to end the deal. Frustration requires no election, because the law discharges both parties from further performance.

Discharge looks forward only, so whatever has already changed hands needs sorting out. The Frustrated Contracts Act does that work. Under section 3, money paid before the discharge is generally recoverable, and money then payable ceases to be payable.

The court can soften that result. Where the party who received or was owed the money spent money performing before the discharge, the court may, if it is just, let that party keep or recover some or all of those sums, but never more than its expenses and never more than the amount paid or payable before the discharge. It can also order payment for a valuable benefit, other than money, that one side received.

The Act does not reach everything. Contracts of insurance, most charterparties and contracts for the carriage of goods by sea, and certain sales of specific goods that perish fall outside it.

What to Do Next: When to Call a Lawyer

Read the contract first. Force majeure, termination, condition and risk-allocation clauses usually answer the question before the doctrine of frustration in Ontario ever comes into play.

Keep performing, or reserve your rights in writing, until you have advice. A party who stops performing on the strength of the doctrine of frustration, and then loses in an Ontario court, becomes the party in breach, as the buyer in Perkins discovered.

Document the event and its effect now. A court will ask whether the change was temporary or permanent, whether anyone could foresee it, and how far it really altered what you promised.

Track the money as well. If frustration does end the contract, deposits, prepayments and expenses become a separate question under the statute, and your records will decide it.

The doctrine of frustration in Ontario rescues very few contracts, and it punishes the party who relies on it and guesses wrong. If an event has upended a deal you signed, contact Cowan before you stop performing.