A tenant prepared its renewal notice on time, then left it behind while the post-dated cheques went out without it. By the time anyone noticed, the option had lapsed and the landlords refused to renew. In 2159117 Ontario Inc. o/a Meaty Eats Inc. v. Cheng, 2026 ONSC 5294, released September 17, 2026, Mathen J. granted relief from forfeiture under s. 20(1) of the Commercial Tenancies Act, R.S.O. 1990, c. L.7, and s. 98 of the Courts of Justice Act, R.S.O. 1990, c. C.43, on one condition (para. 1). The decision maps what a tenant must show when an option is missed.
The lease and the missed deadline
Meaty Eats leased a storefront at 2288 Bloor Street West from Richard Cheng, who has owned the building with his wife since 1999 (paras. 6–7). The respondent landlords are Mr. Cheng and Ida Chang, and Mr. Cheng was their chief witness (paras. 2, 6). The lease ran to December 31, 2026, with two five-year renewal options. Article 17.1 required written notice at least 12 months before expiry, meaning by December 31, 2025, and made the right available only if the tenant was not then in default “beyond the expiration of any applicable notice or cure period set forth herein”. Failing notice, “such option to extend shall be null and void” (paras. 7–8).
The lease gave a fixturing period to December 31, 2021, but renovating the former drugstore took two years, to March 2023 (para. 10). Articles 8.3(a) and (c) barred alterations without written approval and required the tenant to submit drawings and specifications and to carry out the work in accordance with the drawings and specifications the landlord approved (para. 12).
The CEO, Mr. Girimonte, swore he prepared a notice in early December and left it in his office at the store, and the record contains one dated December 1, 2025 (para. 16). On December 12, the office manager emailed Mr. Cheng that the twelve post-dated cheques for 2026 were ready for pick-up, without mentioning the renewal. His son collected an envelope the next day containing only the cheques (paras. 17–18). The mistake surfaced on January 12, 2026, after the Christmas break. A fresh copy was prepared, dated December 13, 2025, to match the day it should have gone out, and emailed on January 13 (paras. 19–21). Mr. Cheng replied that day that the deadline was missed and the only alternative to vacating was buying the building (para. 22).
Clean hands and diligent efforts
The court was not persuaded Meaty Eats had unclean hands. Its actions could be criticized, but they did not rise to a level that would disentitle it from seeking equitable relief (para. 46). Relief turns on the three factors in Saskatchewan River Bungalows Ltd. v. Maritime Life Assurance Co., 1994 CanLII 100 (SCC), [1994] 2 S.C.R. 490, at p. 504 — the applicant’s conduct, the gravity of the breaches, and the disparity between the value forfeited and the damage caused (para. 40). Renewal provisions must be strictly complied with, on 120 Adelaide Leaseholds Inc. v. Oxford Properties Canada Ltd., [1993] O.J. No. 2801 (C.A.), and Doria v. 66 Degrees Inc. (2000), 30 R.P.R. (3d) 287 (Ont. S.C.), so the circumstances for relief are narrower (para. 42). The court held that Meaty Eats had to show “diligent efforts to comply with the lease that were unavailing” (para. 48), on McRae Cold Storage Inc. v. Nova Cold Logistics ULC, 2019 ONCA 452, at para. 10. The court found that Meaty Eats intended to renew, prepared the notice, inadvertently left it out of the package, discovered the error in January, reached out immediately, and was 13 days late (para. 51). That was enough to satisfy that precondition (para. 58).
One explanation was rejected and one evidentiary plank discounted. The CEO’s caregiving duties for his father were not a valid explanation (para. 54). Conversations about renewing carried little weight, because renewal requires written notice and, absent additional context, “one or more conversations about a lease renewal is not evidence of ‘diligent efforts'” (para. 53). The court agreed notice could have gone earlier, which would have been prudent before a busy holiday season, but not that this forfeited its right to seek equitable relief. It was “not unreasonable for Meaty Eats to plan to deliver the renewal notice in December at the same time as the post-dated cheques” (para. 55).
I am persuaded that the botched renewal resulted from sheer inadvertence and, therefore, is different from most of the precedents cited to the court. (para. 56)
Dobcor Investments Inc. v. Bargain Car and Truck, 2023 ONSC 2304, where relief was refused on a nine-day delay, was distinguished because the tenant there offered no explanation (paras. 44, 57).
Gravity and disparity
The court found that the evidence did not show the tenant ensured the landlord received the drawings, which is a default under Article 8.3 (para. 66). But it refused to accept that this inevitably made the tenant unable to renew, since that would let Mr. Cheng rely on a breach he had never communicated to the tenant as a reason to refuse a renewal, regardless of whether the notice was delivered on time (para. 67). Where a landlord stays silent about an asserted breach, a court may conclude he suffered no significant damage (para. 68). Here the default was raised only after the late notice, when his frustrations boiled over (para. 69). The late notice itself was not especially serious. The tenant tried to rectify within 13 days, and no argument was made about any effect from the delay (para. 70).
On disparity, the claimed $2,344,217 cost of being forced to vacate (para. 11) was not made out (para. 77). The only evidence was the CEO’s affidavit and an unauthored one-page chart, with no invoices, financial statements or projections (para. 74). The court instead used a “low, and therefore unassailable, figure”, finding that if Meaty Eats had to relocate by December 31, 2026 it would lose at least $100,000, probably more (para. 77). The 26 job losses claimed were too speculative, though the court accepted the move would be disruptive and might cause some layoffs (para. 78). The landlord produced no evidence that renewing would cost him anything (para. 79).
Relief was granted on condition that the tenant make best efforts to obtain and deliver the drawings and plans the lease requires. It must search its records and contact the City, architects and contractors at its own cost, provide a sworn affidavit within 45 days and give updates every thirty days for three months (para. 85).
Key takeaways for transactional counsel
- Diarize option deadlines independently of the client, and confirm delivery in writing. The notice existed and was dated in time but nobody confirmed it left the building (paras. 16, 51, 61). The court saw nothing unreasonable in planning to send it with the cheques (para. 55), but the single envelope is how it went missing.
- Tell clients that conversations are not notice (para. 53).
- Close out alteration covenants when the fit-out ends. The undelivered drawings were the landlord’s main substantive complaint, and producing them is now a court-ordered condition (paras. 66, 85).
- For landlords, communicate an asserted default when it happens, and seek formal redress (paras. 63, 67–69).
- Document renovation spend contemporaneously. Against a $2.3 million claim, the court would credit only a deliberately conservative floor of “at least” $100,000 on relocation, for want of invoices and financial statements (paras. 74, 77).